Rawhide Creek Trail project to start Monday

city-of-fremont

The City of Fremont’s Rawhide Creek Trail project is tentatively scheduled to begin on Monday (Aug. 15). Construction schedules are subject to change based on weather and site conditions. The project consists of two separate trail segments to be constructed as follows:

West Trail Construction Segment

· Construction along the north side of Linden Avenue from Madison Street to Somers Avenue.

· Construction along the west side of Somers Avenue from Linden Avenue to Ronin Park.

 

East Trail Construction Segment

· Construction along the south side of 19th Street from Garden City Road to Luther Road.

· Construction along the east side of Luther Road from 19th Street to south of 20th Street, then east to Diers Parkway. This portion includes construction along the south side of Elkhorn Drive.

· Construction along the west side of Diers Parkway from Elkhorn Drive south approximately 100 ft.

 

The Contractor plans to work on both segments simultaneously with completion of the trail in 2022. Below is a brief overview of what to expect during construction:

• Temporary lane closures along streets adjacent to trail construction with traffic detours.

• Residents, stakeholders, and businesses with impacted sidewalk and driveway access will be notified prior to restricting access.

• Residents with restricted access will need to park along adjacent streets and or side streets until driveways are reopened.

• For Ronin Park and the business along Elkhorn Drive, construction through driveways will be phased to maintain access at all times.

 

For any questions or inquiries, please contact Public Works at office at 402-727-2638.